The Golden Beach Energy Storage Project is an offshore gas storage project in Gippsland, Victoria, strategically located close to the Longford Gas Hub.

The offshore storage facility will enable new gas to be injected at times of low gas demand (often in summer), and withdrawn again at times of higher demand (usually winter).
Having significant reserves of gas in storage and readily available on peak energy demand days, will help balance the market at times when the wind doesn’t blow and the sun doesn’t shine.
The Project is targeting commencing operations as a flexible storage facility in 2029.



The Golden Beach Energy Storage Project will provide essential supply flexibility and dispatchable energy to an energy market in transition. The project is critical to south-east Australia's net zero objectives and addresses short and long-term projected gas supply shortfalls.
As our energy market transitions to include more renewables and coal-fired power stations exit the market, there are a number of advantages to being able to have deep reserves of gas in storage and available for use when needed:
Seasonality
Security
Flexibility
Critical Infrastructure
Efficient Use of Capital
GB Energy is very conscious of projected gas shortages in south-east Australia later this decade. The Project is targeting commencing operations as a flexible storage facility in 2029.


Offshore drilling
More information about our Offshore Drilling activities can be found here.
The Project has the support of both the Victorian Environment Effects Act 1978 and the Commonwealth Environment Protection and Biodiversity Conservation Act 1999.
The Victorian Minister for Planning determined in May 2021 that the Environment Effects Statement (EES) by GB Energy is appropriate and supports the development of the Project. The EES process is a significant undertaking and underpins the development of the Project according to environmental parameters and processes.
In parallel with the EES process, the Commonwealth Department of Climate Change, Energy, the Environment and Water (now the National Environmental Protection Agency (National EPA) from 1 July 2026) approved the Project under the Environment Protection and Biodiversity Conservation Act 1999, in April 2021 (EPBC ref 2019/8513). An administrative variation to this approval to include new legislation and updated timeframes for Project activities was granted by National EPA in October 2026.
Native title requirements under the Commonwealth Native Title Act 1998 have been met for the Project and approval was received in October 2020.
Under the Victorian Aboriginal Heritage Act 2006, the Project received approval for Cultural Heritage Management Plan (CHMP) #1703 in May 2021. Since this existing CHMP is now outside the statutory 5-year period during which it can be further amended, a new CHMP #21267 was developed, including minor amendments, and was approved in October 2026.
The Onshore Pipeline Licence under the Victorian Pipelines Act 2005 was granted in July 2021 and is awaiting final issue following the completion of the remaining landholder agreements.
The Development Licence for the gas processing facility (also referred to as the compressor station) under the Victorian Environment Protection Act 2017, was approved by the Environment Protection Authority (EPA) Victoria in July 2026. The Development Licence is an EPA permission that allows the gas plant facility to be constructed provided various design, construction and commissioning conditions are met. GB Energy will apply to the EPA for an Operating Licence to cover operations at the gas plant facility in due course.
The Petroleum Production Licence and the Offshore Pipeline Licence under the Victorian Offshore Petroleum and Greenhouse Gas Act 2010 were both granted in October 2026 by the Victorian Department of Energy, Environment and Climate Action (DEECA). In addition, DEECA has also approved the Field Development and Storage Development Plans for the Project. The Storage Development Plan is the first to be approved for offshore petroleum storage in Victorian State waters.
Also, under the Victorian Offshore Petroleum and Greenhouse Gas Act 2010, GB Energy was accepted as Operator of the offshore pipeline and subsea infrastructure by the National Offshore Petroleum Safety and Environmental Management Authority (NOPSEMA) in August 2026 and the Drilling Environment Plan was accepted by DEECA in July 2026.
The Project has been classified as critical energy infrastructure under the Commonwealth Security of Critical Infrastructure Act 2018 and is expected to support the market and the transition to large scale renewable generation.